The intent of this page is to provide information regarding the purpose of and differences between the Invitation for Bid (IFB) and Request for Proposals (RFP) processes used to comply with the State of Alabama Bid Law.  The role of the Purchasing Department is to lead campus partners through all bid processes.  Please contact the appropriate Senior Buyer for guidance if you feel your acquisition will require a competitive bid.

State of Alabama Bid Law

Per Article 5 of Section 41-4 of the Code of Alabama, any purchase request or contract for like or similar products and/or services that exceeds the University’s small dollar purchase threshold of $75,000 must be competitively bid (with limited exceptions). A purchase request or contract cannot be split up to avoid the $75,000 bid threshold. Review Alabama’s Competitive Bid Law.

Competitive Bid is Required If:

  • Purchase value is $75,000 or more
  • No Approved Contract is available through UA, UA System affiliate, State of Alabama or Cooperative
  • Good or Service can be acquired from more than one source
    See Sole Source requirements if only one source is available for your acquisition

 

Request for Proposal vs. Invitation for Bid – THE DIFFERENCE

An Invitation for Bid (IFB) or request for price quotation is used when the specifications of a product, service, or software are already known and when price is the main or only factor in selecting the successful bidder.  A contract is awarded on the basis of price to the lowest responsive and responsible bidder

In contrast, a Request for Proposal (RFP) involves more than a request for price.  An RFP is a solicitation in which the University requests proposals for a particular project or program, and typically anticipates a long-term relationship between the University and the awarded Respondent.

An RFP should reflect the Requester’s strategy and short/long-term business objectives to enable Respondents to provide detailed solutions.  The more detailed the RFP specifications, the more likely proposals will be detailed and accurate.

 

Other factors to consider when comparing IFB to RFP:

IFBRFP
ValueLowest Cost; Good ValueNot always the lowest cost; Best Value
Terms & ConditionsMinimum requirements – no exceptionsCompliance exceptions may be allowed; questions may be submitted for clarification of exceptions
SpecificationsSpecific minimum requirements for performance or design.  Indicating exactly what you wantThe results are determined by the Scope of Work. Asking for respondent to develop and provide a solution.
Evaluation Process Compare costs; compare specs to bid; evaluate bidderEvaluation team; Evaluation criteria set forth in RFP; Respondent demonstrations
Evaluation CriteriaLow bid; must meet specs; lowest responsive and responsible bidder; no changes allowedUnderstanding of requirements; meets minimum requirements; approach and work plan; qualifications and experience; identification of risk; resources; forward-thinking ability, etc.

 

The charts below outline the responsibilities of the following stakeholders through the entire bid process: requesting department, Purchasing department and vendors.

Invitation for Bid (IFB) Chart of Responsibilities
(click image to enlarge)

Invitation for Bid (IFB) Chart of Responsibilities
Request for Proposals (RFP)Chart of Responsibilities
(click image to enlarge)

Request for Proposals (RFP)Chart of Responsibilities

 

 

 

 

Invitation for Bid (IFB) Specification Writing Guidelines and Tips:

Competitive bid specifications should clearly state the minimum requirements necessary to achieve the overall goal of the procurement. Specifications should not be so specific that they limit competition by inclusion of unnecessary unique requirements.

There are multiple types of specifications depending on the type of good or service needed, including, but not limited to:

TypeDescriptionMeasurable Examples
Performance SpecificationsDescribe what a good or service is expected to do by defining desired result using performance indicatorsExamples: power, strength, test methods, standards of acceptability, response time
Design SpecificationsEstablish material and operating requirements of goods needed to meet minimum acceptabilityDimensions, chemical composition, physical properties, materials, ingredients
Combination SpecificationsCombination of performance and design specifications as described aboveSee above
Brand Name or EqualSpecific description including manufacturer, and /or catalog number, and / or model number. Must include “or equal” in order to allow competition

Good quality specifications streamline the procurement process, whereas poor specifications cause unnecessary delay and award complications. The following provides additional guidance in developing quality specifications.

Specification Writing Checklist:

  1. Determine appropriate type of specification
  2. Include only essential information in specifications required for function of purchase
    1. Exclude non-essential information not necessary for function of purchase
    2. Do not be too restrictive – Specifications should be capable of being met by more than one bidder
  3. Write in simple, clear and concise method
  4. Clearly identify goods and /or services sought
  5. Should be organized and categorized
  6. Clearly state intended use
  7. Clearly state required lead time, when applicable
  8. Clearly define any compatibility requirements (e.g. brand / model, connectors, interfaces, etc.)
  9. Identifiable with some brand or specification currently on the market and available, when possible.
    1. Must include “or equal” when a specific product is specified
  10. Clearly define any special terms, conditions, reports, testing, warranty, maintenance, etc.
  11. Clearly define bidder qualification and reference requirements, when necessary
  12. Have clear method for determining if requirements have been met
  13. Be mindful of terminology – Understanding the proper connotation for terms such as “shall” “may” “and” “or” “must” etc.
  14. Use accurate technical and trade terminology
  15. When samples are required, all requirements of samples, including how they will be used in evaluation for award should be included